Mound's Water Plant Came In Under Budget. Why Are Water Bills Still Going Up?

"Regardless of whether the City constructs a water treatment plant, water rates are planned to increase to address a $5 million dollar deficit within the water fund."

That sentence is from a City of Mound staff memo in the October 13, 2026 council packet. It explains what is happening to water costs in Mound better than any headline about the new plant. If you're comparing towns on the west end of Lake Minnetonka, it's easy to assume a $31 million treatment plant means higher water bills. Under the city's own model, it doesn't work that way. The water rate increases planned for 2027 through 2029 are the same with or without the plant. The model pays for the plant mostly through a line on your gas and electric bills, though the council hasn't locked in that approach yet.

This matters to anyone working out what it costs to own a home in Mound. The council is scheduled to adopt the new rates on November 24.

The Bid That Came In Well Under the Estimate

For years Mound planned around an engineer's estimate of $28.5 million for the plant, with $24.5 million of that for construction. On October 13, seven contractors bid between $17.8 million and $19.9 million. That puts even the highest bid below the construction allocation, and the low bid about $6.7 million under it. According to the council minutes, the city's engineering consultants said seven bids was more than they had ever received on a project like this. They gave three reasons the bids came in low. The project went out early, while contractors were looking for work. Demand was soft because of the economy. And materials costs for the Buy America, Build America project had been less affected by tariffs and overseas conflicts than expected.

The council accepted the low bid from Gridor Construction, Inc., $17,798,930, under Resolution 26-71. The resolution also allows a 5% contingency, which brings the maximum contract to $18,688,876.50.

The plant will sit on a four-acre, city-owned site on Evergreen Road behind Sorbo Park. Plans call for about 13,000 square feet, a peak height of 31.5 feet, and capacity to treat 1,500 gallons per minute, or 1.8 million gallons a day. That's according to the Laker Pioneer's coverage of the August 25 meeting where the council authorized bidding.

The lower bid doesn't change the water bill for the next three years, because of how the money is split up.

Why the Savings Don't Show Up on the 2027 Water Bill

Mound's water fund is in debt, and that problem has nothing to do with the plant. The staff memo puts the deficit at $5 million. The Laker Pioneer reported $5.5 million in its late-summer coverage. The October 13 minutes refer to water fund debt of "just under $3Million." Whatever the exact figure, the city's financial consultant, Ehlers, modeled a set of rate increases to get the fund back to positive cash by 2029 and into line with the city's fund balance policy by 2033.

Here are the proposed annual water rate increases under each scenario in the October 13 memo:

Year No plant Plant, $15.5M loan Plant, $13.5M loan
2027 13.5% 13.5% 13.5%
2028 11.5% 11.5% 11.5%
2029 7.5% 7.5% 7.5%
2030 3% 7% 5%
2031 3% 6.5% 4%
2032 3% 5% 3%
2033 3% 3% 3%

For the first three years, all three columns match. The memo says this happens because franchise fee increases go to the plant's debt payments, which leaves water rates to pay down the existing deficit. The plant only starts to affect water rates in 2030. Even then, the gap depends on the size of the loan. Under the smaller-loan scenario, the difference is gone by 2032. A slide recorded in the October 13 minutes made the same point: with the bids this favorable, building the plant "fits within existing planned rate increases."

So the lower bid mostly affects the years after 2029, and the loan size depends on a grant decision that hasn't been made yet.

Where the Plant Actually Gets Paid For

The total project cost is $31.1 million. That includes the Phase 2 infrastructure work along Commerce Boulevard and Evergreen Road toward the Evergreen Water Tower, which Minger Construction has been doing. A 2023 state appropriation of $10.3 million already covered site preparation, which leaves $20.8 million for ratepayers. Federal money takes off a little more: $960,000 in Congressionally Directed Spending from 2023 and a $1,092,000 appropriation in 2026. After that comes the open question, an Emerging Contaminant grant the city expects to be either $3 million or $5 million.

The rest is financed through the Minnesota Public Facilities Authority. The city modeled a 20-year loan at 2%, which it calls a conservative assumption. The low rate is possible because the loan comes from a state appropriation to the PFA, not from a general obligation bond. Under the two scenarios:

  • $3 million grant: about $15.8 million financed, with annual debt service of $960,000
  • $5 million grant: about $13.8 million financed, with annual debt service of $734,000

The city's model pays most of that debt through franchise fees. The memo describes them as fees "paid to gas and electric utilities which are then passed through to the City." They are currently $4 per month, per utility. The proposed schedule raises them to $6 in 2027, $9 in 2029 and $13.50 in 2031, again per utility, per month. A home with both gas and electric service pays the fee on each bill. According to the minutes, city staff described franchise fees as the alternative to funding the plant through property taxes. Council members also discussed charging higher franchise fees to large institutional users.

This affects how you compare towns. If a buyer looks only at Mound's water rate schedule, they miss part of what the plant costs. Under this model, the full picture includes the gas and electric bills, and that charge goes up in steps through 2031.

One detail matters here. Water rate revenue can only be spent on water projects, while franchise fee revenue is unrestricted. The minutes show the council has not fully settled on this approach. One member asked for scenarios that fund the plant through water rates, and staff agreed to bring back options showing how each one affects individual utility users.

What the Money Buys

The plant addresses two problems in Mound's water. The city's Water Treatment Plant Updates page, last updated October 15, 2026, says the supply meets Safe Drinking Water Act primary standards but has manganese above the Minnesota Department of Health's recommended health advisory levels. The supply is also high in iron, which the city links to discoloration.

The Minnesota Department of Health explains its manganese guidance values, and how they differ for households with infants, on its manganese in drinking water page. The page also says those values are not requirements for public water systems. Anyone with questions about their own household should start there.

In the October 13 council minutes, city staff described the plant as "a taxpayer dollar solution instead of in-home water treatment solutions," and as a way to protect both public and private infrastructure. When the plant comes online, the city expects it to handle iron and manganese for the whole system, so individual homes won't have to.

Here's the current baseline for the water portion of the bill. Mound's 2026 utility rates list a residential quarterly base charge of $72.45. Usage is charged at $6.61 per 1,000 gallons from 1,000 to 8,000 gallons, $8.05 from 8,001 to 14,000, and $10.06 above 14,000. The proposed increases above would apply on top of this schedule once adopted.

The Dates Still Ahead

Nothing above is final until the council votes. Here's the schedule listed in the October 13 minutes:

  1. November 10, 2026: Financial management plan and utility rate study update, including how the plant will be funded
  2. November 24, 2026: Utility rate adoption
  3. Spring 2027: Construction begins
  4. 2028: Interior construction, with the plant going online that year

The Laker Pioneer reported a completion target of fall or winter 2028. According to the same coverage, the Minnesota Department of Health approved the plant permit in June, and the city approved a conditional use permit on April 14. Those two approvals mean the remaining questions are mostly about financing, and November is when they get answered.

FAQ

Would Mound's water rates go up if the plant weren't built? Yes. The city's model shows 13.5% in 2027, 11.5% in 2028 and 7.5% in 2029 in the no-plant scenario too, because those increases address the existing water fund deficit.

Why would the plant's cost show up on gas and electric bills? The city's proposal sends franchise fee increases, which are collected through gas and electric utilities, to the plant's debt payments. The proposed fee goes from $4 to $6 per utility, per month, in 2027. The council can still choose a different mix when it adopts rates.

What decides whether rates rise faster after 2029? Mostly the size of the Emerging Contaminant grant. With $5 million, the modeled rate increases match the no-plant path by 2032. With $3 million, the increases stay higher through 2032.

This post is general information about proposed city fees and rates. It isn't legal, tax or financial advice, so check with the city and the right professionals about how these numbers apply to your situation.

If you're weighing a home in Mound against nearby communities and want carrying costs like these included in the comparison, Lynn Reiners can go through the numbers with you, including what the council adopts on November 24. Schedule your personal market consultation with Lynn.

Work With Lynn

Lynn Reiners remains steady, reliable, responsive, professional, and proactive in every type of transaction. Call her now to start your real estate journey.

Follow Me on Instagram